Pakistan court extends stay against construction of nuclear plants
A local court
here has extended for another week its stay order restraining the Pakistan Atomic Energy Commission {PAEC}
from carrying out work on the two nuclear power plant projects in Karachi
without adhering to environmental laws.
The Sindh high court on Saturday extended the
stay after hearing the PAEC counsel
who said that the project was duly approved by the International Atomic Energy
Agency.
A two-judge panel of chief justice Maqbool Baqar
and justice Shahnawaz Tariq was hearing a petition challenging the environmental
impact assessment {EIA} report of the Sindh Environmental Protection Agency {Sepa}
which approved the two plants. the
bench had directed the government not to start work unless they met the
requirements set under Section 12 of the Sindh Environmental Protection Act,
2014.
The PAEC
recently started preparing sites for the two nuclear power plants named K-2 and
K-3 adjacent to the Karachi Nuclear
Power Plant {KANUPP}.
The pakisthan government is also considering
building two more plants K-4 and K-5 in the same locality.
PAEC counsel Anwar Mansoor Khan told the judges
that France was also using the same technology and providing over 400 megawatts
to its neighbouring countries.
He said the project was aimed at providing
electricity to people in Karachi on a priority basis and part of the
government's policy to make the electricity available in every part of the
country.
the counsel said that a guideline already
available to ensure life and property of the people was strictly being followed
by the government.
According to the petition, the reactors had
purportedly been designed and would be built by the China National Nuclear
Corporation on a design known as ACP-1000, which was not operating even in
China.